PRE-CONSTRUCTION | 3-4 months
Lender pre-approval
Select builder/architect
Scout locations to build
Review plans online
Refine blueprints
Pick selections with designer
Contract signing
*By selecting one of our preferred plans this can be expedited to 1-2 months
SITE PREPARATION | 1-2 months
Pulling permits
Land clearing and grading
Temporary construction driveway
Utilities installation
Survey
FOUNDATION | 3-4 weeks
Dig footings
Pour concrete in footings
Lay CMU block
Add brick if desired
FRAMING | 1-2 months
Frame construction
Roofing
Flooring system installed
Windows & exterior doors
FINISHES | 2-3 months
Exterior paint or staining
Interior finishes (plumbing, electrical, & HVAC) Painting and touch-ups
Final inspections
CLOSING | 1 day
Final walkthrough
Move in!